Date: |
Name: |
License #: |
Job #.: |
# of Stories: |
|
Inspection Description |
Frequency |
Relevant Code, Section Or Standard |
1 |
General Tasks |
||
1.1 |
Verify embedded fall-arresting systems have been inspected as it relates to use for concrete installation. Shop drawings. Contractor maintenance log |
On-going |
3310.9 |
1.2 |
Maintain a concrete safety log book which lists activities that shall be conducted in coordination with the site safety manager or coordinator |
Daily |
3310.8.4 |
1.3 |
Adequate lighting |
Daily |
3310.9 |
1.4 |
Adequate ventilation |
As required |
3310.9 |
1.5 |
Housekeeping |
Daily |
3303.4 |
1.6 |
Pre-Storm planning, high winds |
As required |
BB2013-011 |
1.7 |
Concrete washout water, collection, containment, disposal |
As required |
3303.15 |
1.8 |
Underpinning sequence/detail drawings on site |
As required. |
3304.11 |
2 |
Site Safety Provisions |
||
2.1 |
Monitor that required fall protection systems in place |
On-going |
3308 |
2.2 |
Monitor workers using required fall protection systems |
On-going |
3310.9 |
2.3 |
Monitor hoisting and rigging operations performed in a safe manner |
As required |
3316 |
2.4 |
Extra shores or other material and equipment are available in the event of an emergency |
Daily |
3305.3.6.2.1 |
2.5 |
Building materials properly piled and tied or contained |
Daily |
3305.3.6.2.3 |
2.6 |
Emergency egress maintained |
On-going |
3310.9 |
2.7 |
Escape hatches |
As required |
3303.6 |
2.8 |
Handrails, mid-rails and kickboards in place and secure |
Daily |
3310.9 |
2.9 |
Formwork erection and stripping signage clearly displayed |
As required |
3310.9 |
2.10. |
Rebar ends capped to prevent impaling. |
On-going |
3310.9 |
3 |
Installation of Formwork |
||
3.1 |
Verify formwork drawings are available. Including shores, re-shores, foundations |
Prior to formwork installation |
3305.3.1.5; ACI 318; 6.1.5 |
3.2 |
Verify formwork drawings are signed and sealed when required by Code |
As required prior to formwork installation |
3305.3.2.1 |
3.3 |
Verify existing structure adjacent to concrete placement has been inspected and evaluated by a registered design professional prior to use as a form. Design drawings prepared |
Prior to formwork installation |
3305.3.1.2.1 |
3.4 |
Verify formwork inspected by a competent person and shores are installed as per shop drawings |
Prior to reinforcement placement |
3305.3.3.1 |
3.5 |
Verify visual observations of formwork were conducted by formwork designer at the minimum intervals |
See 3305.3.3.2.1 |
3305.3.3.2; 3305.3.3.2.1 |
3.6 |
Verify any formwork discrepancies have been resolved |
Prior to reinforcement placement |
3305.3.3.2.2 |
3.7 |
Unsafe conditions; notify contractor; contact DOB if required |
Continuous |
3305.3.4.4 |
3.8 |
Monitor the required guardrail systems are in place on the forming and placement floors |
On-going |
|
3.9 |
Ramps, runways and platforms comply with 3315. Designed by qualified person when buggies used |
On-going |
3305.3.1.4 |
3.10 |
Inspection of concrete formwork by Concrete Safety Manager |
On-going |
RCNY 3310-02. e, 9. |
4 |
Placement of Reinforcement |
||
4.1 |
Verify required shop drawings are available on site |
Prior to reinforcement placement |
3310.9.1 |
4.2 |
Monitor that the workers performing reinforcement bending, cutting, welding and reinforcement placement operations on the working deck are working in a safe manner |
On-going |
3310.9.1 |
4.3 |
Verify reinforcement placement operations are performed in a safe manner |
Continuous |
3310.9.1 |
4.4 |
Verify concrete special inspector inspected and signed-off on final reinforcement placement |
Prior to concrete placement |
1907.5 |
5 |
Placement of Concrete |
||
5.1 |
Verify concrete special inspector is present for concrete placement. |
Each placement |
3310.9.1 |
5.2 |
Verify DOB licensed concrete testing lab is present to sample and test. |
Each placement |
3310.9.1 |
5.3 |
Pumping operations. |
|
3310.9.1 |
5.4 |
Verify pump operator and placement crew have participated in a preplanning meeting for pumping operations. Verify preplanning meeting for concrete pump operations occur at initial start-up of concrete pumping operations. |
Prior to first pumping operation |
3310.9.1 |
5.4.1 |
For concrete pumping operations which involve lubricating grout (e.g. concrete pumped though a placement boom). |
Each placement |
3310.9.1 |
5.4.1.2 |
Verify the contractor supplied sufficient grout discharge boxes on-site to receive 100% of the volume of the lubricating grout actually placed in the boom (and hoses, etc.), regardless of the volume indicated on delivery ticket(s). |
Each placement |
3310.9.1 |
5.4.1.3 |
Verify the contractor provided the special inspector of the concrete pour with sufficient notice |
Each placement |
3310.9.1 |
5.4.1.4 |
Confirm the special inspector is on site to perform the required special inspections |
Each placement |
3310.9.1 |
5.4.1.5 |
Confirm that the special inspector has observed the concrete exiting the hose and that he has identified it as concrete exhibiting a uniform matrix of aggregate before commencement of placement of the structure |
Each placement |
3310.9.1 |
5.5 |
Verify pump equipment has been inspected |
Prior to each use |
3310.9.1 |
5.6 |
Verify hoses and connections have been inspected |
Prior to each use |
3310.9.1 |
5.7 |
Monitor pumping operations performed in a safe manner |
On-going |
3310.9.1 |
5.8 |
Monitor concrete buckets, hoppers, chutes and buggies are inspected, cleaned and in proper working order |
Prior to each placement |
3310.9.1 |
5.9 |
Monitor concrete placement is performed in a safe manner |
On-going |
3310.9.1 |
5.10. |
Monitor power buggies operated in a safe manner |
On-going |
3310.9.1 |
5.11 |
Monitor formwork is inspected during concrete placement for potential problems |
On-going |
3310.9.1 |
5.12 |
Verify the designated signalmen are in place when a crane is being used for lifting |
As required |
3310.9.1 |
5.13 |
Cold weather requirements |
As required |
1905.12 |
5.14 |
Hot weather requirements |
As required |
1905.13 |
5.15 |
Verify rate of placement not exceeded per drawings |
On-going |
3305.3.2.3 |
6 |
Stripping Operations |
||
6.1 |
Monitor that the horizontal netting conforms to Code before commencing stripping operations |
On-going |
3310.9 |
6.2 |
Verify formwork removal procedure |
Prior to stripping |
3305.3.5.1 |
6.3 |
Monitor that in-place concrete strength has been evaluated and accepted in accordance with removal schedule |
Prior to stripping |
3305.3.5.1.3 |
6.4 |
Verify structural members have acquired sufficient strength to safely support their own weight and external loads |
Prior to stripping |
3305.3.5.5 |
6.5 |
Monitor stripping operations are performed in a safe manner |
On-going |
3305.3.5.4 |
6.6 |
Debris contained and removed at reasonable intervals |
On-going |
3305.3.6.6 |
6.7 |
Stripping not performed more than three stories below the story being formed |
On-going |
3305.3.6.6 |
6.8 |
Special considerations for prestressed members |
As required |
3305.3.5.3 |
7 |
Reshoring Operations |
||
7.1 |
Verify reshoring plan is available |
Prior to stripping |
3305.3.6.8 |
7.2 |
Monitor reshores within 10 feet of building edge are secured, banded and tied to the structure |
Daily |
3305.3.6.1.2 |
7.3 |
Monitor wedges are not used for reshores within 10 feet of building edge |
Daily |
3305.3.6.1.3 |
7.4 |
Monitor appropriate number of floors have been reshored. |
Daily |
3305.3.6 |
7.5 |
Verify reshores were inspected by competent person designated by the contractor |
Prior to forming next level |
3305.3.3.1 |
7.6 |
Verify visual observations of formwork were conducted by formwork designer at the minimum intervals |
Prior to forming next level |
3305.3.3.2 |
7.7 |
Stresses. Ensure shores not located improperly causing stress reversals or inducing tension at unreinforced portion of structural member(s) |
On-going |
3305.3.6.1.4 |
7.8 |
Reshores perpendicular to surface they are supporting |
On-going |
3305.3.6.1.5 |
7.9 |
Reshores braced and plumb |
On-going |
3305.3.6.3 |
8 |
Material Handling |
||
8.1 |
Monitor safe handling of shores, reshores, formwork and reinforcement |
As required |
3310.9.1 |
8.2 |
Monitor proper storage of shores, reshores, formwork and reinforcement on working floors |
Daily |
3310.9.1 |
8.3 |
Monitor floors not overloaded by excessive storage |
Daily |
3310.9.1 |
8.4 |
Monitor fall protection methods employed at edges left exposed for hoisting are in place |
Daily |
3310.9.1 |