Regardless of how the project work is portioned out, administration of the work remains the responsibility of the Registered Design Professional (RDP) who is the Applicant of Record (Applicant) in responsible charge or has verified Code and Zoning compliance of the drawings and installations for the project. Although there may be some specific projects that do not involve architectural or structural work, which may be completed by other professionals, it is important that the RDP maintain control of the entire project and understand when this applies under Department and NYS regulations.
This section contains a list of tasks that provide compliance with the Construction Codes and other regulations discussed in the Project Guidelines.
Provide ‘reference only’ documents of legal existing conditions. These will speed up the plan review process by reducing comments and the number of back and forth checks.
An Initial Survey that is no older than 90 days must be submitted.
Required Documents. Based on scope of work, supporting documents or deferred submittals must be completed in order to obtain a permit. The following documents must be submitted:
Site Plan/ Builders Pavement Plan
Architectural Survey
BPP-1 Checklist
ST-1 Street Tree Checklist
Colored photos signed, sealed and dated
Get a printable version.
Required Documents: Based on scope of work, supporting documents or deferred submittals must be completed in order to obtain a permit. The following may be required if applicable:
NYC Department of Transportation (DOT) approval
BPP-5 Authorization to DOT
Post Approval Amendments: If the approved work has substantive or significant changes, make sure to submit revised drawings and obtain a Post Approval Amendment (PAA).
Get a printable version.
As-Built Submission: If the completed project has changes that are not considered as minor and requires an “As-Built” submission, make sure to submit revised “As-Built” drawings prior to project sign-off.
Following completion of the project, a Final Survey showing the actual work must be submitted.
Final inspection conducted by DOB inspectors.
Required documents for sign-off:
Get a printable version.