Design Professional Checklists:
Other Construction Equipment
Regardless of how the project work is portioned out, administration of the work remains the responsibility of the Registered Design Professional or Registered Contractor, who is the Applicant of Record in ‘responsible charge’ or has verified Code compliance of the drawings and installations for the project. Although some specific projects that do not involve architectural or structural work, which may be completed by other types of NYS Registered Professionals, it is important that the design professional who is Applicant of Record maintain control of the entire project.
This section contains a list of tasks that provide compliance with the Codes and other regulations discussed in the Project Guidelines.
Checklists include:
Prior to Application Approval Checklist
- Provide ‘reference only’ documents of legal existing conditions. These will speed up the plan review process for repairs by reducing comments and the frequency of repeat reviews.
- Based on the project scope of work, include all applicable Special/Progress Inspections and commissioning statement.
- Minimize deferred submittals to the extent possible to avoid construction delays.
- Although the Registered Design Professionals are only required to show the final construction documents, the Applicant of Record should stamp and sign all formal submittals to DOB to demonstrate he/she has exercised responsible charge as required.
Get a printable version.
Pre-Permit & On-going Project Work Checklist
Pre-Permit
Required Documents: Based on scope of work, supporting documents or deferred submittals must be completed in order to obtain a permit. The following may be required:
- MTA – Transit Authority Approval
- LPC – Landmark approval/authorization
- DEP, or OER authorization
- FDNY – Notification or Letters of No Objection
- Tenant/Occupant Protection Plan
- Public Design Commission Approval
- SRO MD Anti-Harassment checklist for residential
- HPD Certificate of No Harassment for residential
On-going
Post Approval Amendments: If the approved work has substantive or significant changes, submit revised drawings and obtain a Post Approval Amendment (PAA).
Get a printable version.
Project Completion Close-out Checklist
- Verification: The applicant shall verify that the Contractor completed the work in which the Construction Equipment was required for and passed all required inspections prior to the Contractor obtaining a final sign-off of the completed work.
Get a printable version.