As per Chapter 17 of the Building Code, alteration work may require certain Special and Progress Inspections to be performed during and at the end of construction as outlined in the table below. Prior to approval for a permit, the Applicant of Record is required to identify all required Special and Progress Inspections per BC 1704.1. Prior to DOB permit issuance, the owner must typically engage a registered Special Inspection Agency (SIA) who will take responsibility for the Special and Progress Inspections. The applicant of record may perform these inspections if they are also an SIA. Inspection discrepancies and hazardous conditions shall be reported for correction to the super-intendent of construction, as well as to the Site Safety Coordinator or Site Safety Manager per BB 2016-006 and 1 RCNY 101-06. Per BC 1704.1.2, the Contractor cannot hire the special inspector.
Based on the scope of work, an alteration project may be required to comply with the following Special and Progress Inspection requirements: See BB: 2014-017 for a more comprehensive Table.
Structural Steel |
May include steel welding, High Strength Bolting and Steel Details (BC 1704.3). |
Concrete: Cast-In-Place |
Required where the total concrete placement on a given project is more than 50 cubic yards or other conditions. (BC 1704.4) |
Concrete – Precast and Pre-stressed |
Are subject to Special Inspections in accordance with Section BC 1704.4. |
Masonry |
Load bearing masonry, glass unit masonry and masonry veneer shall be inspected and verified in accordance with the requirements of sections BC 1704.5.1 through BC 1704.5.3, depending on the structural occupancy category of the building or structure |
Wood – Installation of High-Load Diaphragms |
High-load diaphragms shall be installed with special inspections as indicated in Section BC 1704.6.1. Limited to 5-story construction. |
Wood – Installation of Metal-Plate-Connected Trusses |
Metal-plate-connected wood trusses shall be subject to special inspection in accordance with Section BC 1704.6.2.1 and BC 1704.6.2.2. Limited to 5-story construction. |
Wood – Installation of Prefabricated I-Joists |
Are subject to Special Inspections in accordance with Section 1704.2 and the requirements of Section BC 2303.1.2 (BC 1704.6.3). Limited to 5-story construction. |
Subgrade inspection, subsurface conditions, borings and test pits |
Are subject to Special Inspections in accordance with Section BC 1704.7 |
Deep Foundation Elements |
Are subject to Special Inspections in accordance with Section BC 1704.8. |
Helical Piles |
Are subject to Special Inspections in accordance with Section BC 1704.8.5. |
Vertical Masonry Foundation Elements |
Are subject to Special Inspections in accordance with Section BC 1704.9. |
Sprayed Fire-resistant Materials |
Special Inspections for sprayed fire-resistant materials applied to floor, roof and wall assemblies and structural members shall be in accordance with Sections 1704.11.1 through 1704.11.7. |
Mastic and Intumescent Fire – resistant Coatings |
Special inspections for mastic and intumescent fire-resistant coatings applied to structural elements and decks shall be in accordance with AWCI 12-B. Special inspections shall be based on the fire-resistance design as designated in the approved construction documents as per BC 1704.12. |
Exterior Insulation and Finish Systems (EIFS) |
All EIFS applications installed more than 15 feet above adjacent finished grades and alterations to existing EIFS installations more than 15 feet above adjacent finished grades shall be in accordance with Section BC 1704.13. |
Alternative Materials |
Special inspections for construction materials and systems that are alternatives to those prescribed in the code, per BC 1704.14 |
Smoke Control Systems |
Smoke control systems shall be tested by a special inspector in accordance with Sections BC 1704.15.1 and BC 909. |
Sprayed Fire-resistant Materials |
Special Inspections for sprayed fire-resistant materials applied to floor, roof and wall assemblies and structural members shall be in accordance with Sections 1704.11.1 through 1704.11.7. |
Mechanical Systems |
Mechanical systems requiring a certificate of compliance in accordance with AC 28-116.4.1 of the Administrative Code shall be inspected for conformance with the approved construction documents as per BC 1704.16. |
Fuel Oil Storage and Fuel – Oil Piping Systems |
Fuel-oil storage equipment, including tanks, pumps, valves, transfer, return, fill and vent piping, hangers and bracing, fill and vent terminals, and related systems regulated by MC 1308 of the New York City Mechanical Code. See BC 1704.17 for additional information. |
High - Pressure Steam Piping (Welding) |
High-pressure-steam piping and high temperature hot water piping shall be subject to a special inspection in accordance with BC 1704.18 |
High Temperature Hot Water Piping (Welding) |
High-pressure-steam piping and high temperature hot water piping shall be subject to a special inspection. See BC 1704.18 for additional information. |
High – Pressure Fuel – Gas Piping (Welding) |
Per FGC 403.1.1, all welded gas distribution piping is subject to a special inspection. See BC 1704.19 for additional information. |
Structural Stability – Existing Buildings |
Alteration of existing structural systems or elements, such as columns, girders, beams, bearing walls, etc. where the stability or integrity of a structural system is to be temporarily diminished, in accordance with Sections 1704.20.6 through 1704.20.10. |
Excavations – Sheeting, Shoring, and Bracing |
Methods employed to protect the sides of excavations shall be subject to Special Inspections in accordance with Sections BC 1704.20.6 through BC 1704.20.10. |
Underpinning |
Underpinning of structures shall be subject to special inspections in accordance with Sections BC 1704.20.6 through BC 1704.20.10. |
Mechanical Demolition |
Where mechanical demolition equipment, other than handheld devices, is to be used in the full or partial demolition of a building from within the building, or is to be used within the building to remove debris or move material, such demolition operation shall be in accordance with BC 1704.20.4. |
Raising and Moving of the Building |
A periodic special inspection shall be required in accordance with Sections BC 1704.20.6 through BC 1704.20.10 where the lowest above-grade floor or the lowest subgrade floor of a building is to be raised, lifted, elevated or moved. |
Soil Percolation Test – Private On-site Storm Water Drainage Disposal Systems and Detention Facilities |
Soil percolation tests shall be performed in accordance with BC 1704.21.1.2. |
Private On-site Storm Water Drainage Disposal Systems and Detention Facilities Installation |
Private on-site storm water disposal systems and detention facilities Special Inspections shall be performed in accordance with BC 1704.21.2 |
Individual On-site Private Sewage Disposal System Installation |
Individual on-site private sewage disposal systems shall be inspected in accordance with the rules of DOB per BC 1704.22. |
Soil Percolation Test – Individual On-site Private Sewage Disposal Systems |
Soil percolation tests shall be performed in accordance with BC 1704.22. |
Sprinkler Systems |
Sprinkler systems shall be inspected in accordance with BC 903 and BC 1704.23. See Sprinkler Project Guideline. |
Standpipe Systems |
Per NYC BC 1704.24, Standpipe systems Special Inspections are required to verify installation of materials, fitting hangers’ assemblies and signage, are per approved documents. In addition, Special Inspection must ensure that painting of system complies with BC 905.11 and BC 905.11.5. This portion of the inspection may be conducted periodically at incremental stages matching the progress of the work. Special inspector shall witness all required tests, both Hydrostatic* and flow tests and ensure submission of Form FP 84 to FDNY. See Standpipe Project Guideline. |
Heating Systems |
New heating systems shall be tested in accordance with BC 1704.25. See Mechanical Project Guideline. |
Chimneys |
Chimneys shall be subject to a special inspection in accordance with BC 1704.26. |
Fire-resistant Penetration and Joists |
Special Inspections for penetration of fire-resistant elements and assemblies; and related fire-stops in accordance with Sections BC 1704.27.1 and BC 1704.27.2. |
Flood Zone Compliance |
Special Inspection for flood zone compliance shall be as required by BC Appendix G and BC 1704.29. |
Luminous Egress Path Markings |
The installation of photo luminescent egress path markings shall be subject to special inspection in accordance with BC 1704.30. The special inspector shall verify that approved photo luminescent egress path markings were provided and installed in accordance with DOB rules and regulations, the approved construction documents, and manufacturer’s instructions. |
Emergency and Standby Power Systems (Generators) |
Emergency and standby power systems shall be installed in accordance with the New York City Electrical Code, NFPA 110 and NFPA 111, and BC 2702. See Emergency Backup Power Systems (Generators) Guideline. |
Footings and Foundation |
Footing and foundation inspections shall be made after excavations for footings are complete and any required reinforcing steel and required forms are in place as per BC 110.3.1. |
Structural Wood Frame |
Inspections shall be performed for wood structural framing to determine compliance with the approved construction documents as per BC 110.3.3. |
Fire-Resistance Rated Construction |
Fire-resistance-rated partitions, floors, ceilings, shafts, and shutters as per BC 110.3.4. |
Aluminum Welding |
The Special Inspections for structural aluminum elements of buildings and structures shall be as required by Section BC 1704.28.1. |
Post-installed Anchors |
The installation of post-installed mechanical anchors, adhesive anchors, and screw anchors shall comply with Table BC 1704.32. The special inspection shall include the verification of compliance with approved construction documents and standards established by the commissioner pursuant to Section AC 28-113.2.2 and BB 2014-018, BB 2014-019. |
Seismic Isolation Systems |
There shall be periodic special inspection during the fabrication and installation of isolator units and energy dissipation devices, if used as part of the seismic isolation system as per BC 1707.8 |
Concrete Design Mix |
Concrete mix designs shall be in accordance with BC 1905.3 and BC 1913.5 (former TR3 form). |
Concrete Sampling and Testing |
Concrete sampling and testing shall be in accordance with BC 1905.6 and BC 1913.1.10 (former TR2 form). |
Preliminary |
Preliminary inspections shall be in accordance with AC 28-116.2.1 and BC 110.2. |
Lowest Floor Elevation |
In areas of special flood hazard, upon placement of the lowest floor, including the basement (for flood zone purposes), and prior to further vertical construction, the elevation inspection report required in Item 1 of Section BC G105.3 of BC Appendix G shall be submitted to DOB per BC 110.3.2. |
Public Assembly Emergency Lighting |
Public Assembly Emergency Lighting shall be in accordance with AC 28-116.2.2. |
Final Inspection |
There shall be a final inspection of all permitted work. Final inspections shall comply with AC 28-116.2.4. |
Energy Code Compliance Inspections |
|
In accordance with AC 28-116.2 and BC 110.1, the Department requires inspections at various stages of completion, as well as for final completion of all permitted work. Based on the scope of work, the following inspections from different DOB Inspection Units may be required:
Cranes and Derricks Inspections
Electrical Inspection
Elevator Inspection
Fuel Gas Inspections - including gas piping rough-in
Oil Burning Equipment
Contractors and property Owners are responsible for scheduling and completing all required inspections. Prior to scheduling such an inspection, Contractors must:
Confirm that all construction work completed matches the approved drawings.
Periodically check that no safety hazards exist on the active construction project.
Confirm that work complies with Code and other requirements.
Confirm that all Energy Code requirements are met.
During the course of completing mechanical system work, Contractors should check the following to ensure regulatory and Code compliance with NYC Energy Conservation Code: Commissioning is required on newly installed systems with a cumulative input heating capacity >600,000 BTU/h and/or cooling capacity > 480,000 Btu/h.
Commissioning preliminary report: Must be submitted to DOB prior to mechanical sign-off.
Commissioning final report: Must be submitted to the Department 18 months after certificate of completion, as required by NYCECC Section C408.
Contractors have the option to either require a DOB Inspection or submit a self-certification of the completed work, if applicable. Contractors opting to self-certify must submit a notice of intent to self-certify, with the dates of these self-certified inspections to DOB, and follow-up with the submission of results for self-certified inspections. The following inspections may be self-certified:
Plumbing and boiler - Work Progress and Final Inspection
Waste and Water systems - Work Progress and Final Inspection
Sprinkler work - Work Progress and Final Inspection
Standpipe work - Work Progress and Final Inspection
DOB Inspection Units conduct a random audit of all self-certified notices to ensure compliance of inspected work with code and regulations.
With respect to Contractor self-certification of inspections for plumbing systems, please note that no such inspections are allowed for gas systems, fire pumps, or pressure testing of piping. See the Guidelines of those systems for more information.
DOB inspections may be required during various project stages. Such inspection requests may be made online and any objections raised may be resolved on-line.
The results of Special Inspection may be submitted online by a Special Inspection Agency.
If the applicant elected to self-certify the required DOB inspections, an online notice of intent to self-certify must have been submitted at the project start. Such self-certified inspections may be audited; audit results will be provided to applicant and must be resolved prior to final sign-off.
Depending on the above, DOB or the applicant shall complete the final sign-off inspection to close the project.
The applicant must submit revised “As-Built” drawings, indicating all changes, prior to project sign-off.
An online tool for scheduling appointments for required DOB inspections must be used. This system, DOB NOW: Inspections provides the ability to request and cancel appointments online, as well as view inspection results and documentation.