2013 Buildings Bulletins |
|||
Issuance |
Type/ |
Relevant Code Sections |
Purpose |
HMC 27-2004(2)(21) |
This bulletin clarifies the enclosure requirements for kitchenettes and minimum dimension for living room and habitable space in a multiple dwelling. |
||
March 19, 2013 |
OTCR / Related to: OTCR/Buildings Bulletin 2015-014 |
BC 1901 |
This document establishes design and acceptance criteria of externally bonded fiber-reinforced polymer (FRP) systems for structural repair and upgrade of concrete and masonry elements. |
March 19, 2013 |
OTCR / Supersedes: Related to: Related to: OTCR/Buildings Bulletin 2015-020 |
AC 28-113.2.3 |
This document establishes acceptance criteria for the use of polypropylene (“PP”) piping systems in hydronic piping, irrigation systems, and water recycling distribution piping systems as alternative materials in the 2008 NYC Construction Codes. |
March 25, 2013 |
OTCR / Supersedes: |
AC 28-113.2.3 |
This document establishes acceptance criteria for gas-fired direct vent space-heating appliances used for providing heat in rooms for sleeping purposes in accordance with the 2008 NYC Construction Codes. |
April 26, 2013 |
HMC 27-2004 |
This document clarifies that hostel-type accommodations are considered to be illegal rooming units, pursuant to Section 27-2077 of the Housing Maintenance Code, except for certain grandfathered units and units operated by non-profit institutions and city agencies. |
|
April 29, 2013 |
FGC 102.4 |
This bulletin establishes procedures and requirements for work involving fuel gas distribution piping located within fire-resistance-rated construction in existing buildings undergoing alterations, replacement, and repairs. |
|
June 3, 2013 |
See Table 1 below |
This bulletin seeks to clarify the term approved as it pertains to materials. |
|
June 13, 2013 |
OTCR / Supersedes: |
AC 28-113.2.1 |
This document establishes acceptance criteria for flexible fuel-oil piping systems as alternative materials to the 2008 NYC Construction Code. |
June 21, 2013 |
OTCR / Related to: OTCR/Buildings Bulletin 2015-015 |
AC 113.2.3 |
This document establishes acceptance criteria for attendant operated automobile parking lifts installed in accordance with the 2008 NYC Construction Codes. |
August 12, 2013 |
Zoning / Rescinded by: Zoning/ |
ZR 32-15 |
This bulletin clarifies zoning requirements when establishing yoga studios in buildings or portions thereof. |
August 23, 2013 |
Operational / Related to: |
BC 1601.1 |
This document clarifies the pre-storm planning for construction sites. |
September 13, 2013 |
BC 1019.1.2 |
This document clarifies 2008 Code and 1968 Code requirements with regard to fire alarm equipment and panels, data gathering panels, terminal transmission boxes, and all associated wiring in stair enclosures. |
|
October 4, 2013 |
AC 28-116.2.3.2 |
To clarify special inspection requirements related to raising, lifting, elevating, or moving buildings. |
|
October 24, 2013 |
Operational / Superseded by: Operational/ |
BC 1626 |
To clarify the process of submittal and permitting of projects that require Structural Peer Review per BC Section 1627. |
December 2, 2013 |
Technical/ Rescinds: |
This bulletin rescinds 28 past Technical Policy and Procedure Notices (TPPNs) that are no longer applicable. List of rescinded TPPNs: 1/87 4/87, 5/87, 6/87, 7/87, 3/88, 4/88, 16/88, 17/88, 18/88, 2/89, 4/91 (issued 6/25/1991), 4/91 (issued 7/26/1991), 2/92, 4/92, 10/92, 5/93, 8/93, 14/93, 1/94, 4/94, 10/94, 12/94, 2/95, 3/95, 4/95, 1/96, and 1/00. |
|
December 5, 2013 |
EC 225.10 |
This bulletin clarifies the acceptable use of Rigid Nonmetallic Conduit as permitted conduit for service-entrance conductors, outside feeders, and outside branch circuits on buildings located in a corrosive environment. |
|
December 9, 2013 |
BC 3319.4 |
This bulletin clarifies the process to file a certificate of approval application for a tower crane. |
|
December 26, 2013 |
BC 109.3.4 |
This document establishes acceptance criteria for phase change material (PCM) as an alternative material not prescribed in the 2008 NYC Construction Codes. |